Restoring Grout on Footings of an HTF Tank

HTF liquid tanks are subjected to continuous temperature changes and variations in the amount of liquid they store, causing cyclic efforts in the supports. Alphatec Engineering was commissioned by Ute Andasol in Granada, Spain, to restore the grout on the footings of an HTF tank at the Andasol concentrated solar power station.

This renewable energy project involved a 31WTE22 BB001 vessel (400 mยณ) used in the plantโ€™s thermal storage system, where maintaining a stable foundation is vital for long-term performance.

Features

Client

UTE Andasol III

Final user

Marquesado Solar

EPC

MAN Solar Milennium Duro Felguera s.a. energรญa

Project

Restoring Grout on Footings of a HTF Tank

Equipment

31WTE22 BB001 VESSEL 400 m3

Work period

February 2015

Location

Aldeire Granada, Spain

01

Key Issues

The HTF tanks, continuously exposed to temperature fluctuations and varying liquid levels, experience cyclic loads that put considerable stress on their supports. The anchoring and insulation system on the tankโ€™s sliding supports had deteriorated over time, with the following problems identified:

Deteriorated Interface

The absence of a proper bond between the cementitious grout and the sliding plates led to progressive cracking of the insulation layer.

Loose Anchor Bolts

Poor anchorage contributed to excessive movement during contractionโ€“dilatation cycles, resulting in elevated loads on the footings.

Stress Concentration

The steel base plates were acting as stress concentrators, further exacerbating the degradation of the insulation material.

02

Solution and Repair Process

Alphatec Engineering proposed a comprehensive repair strategy to rehabilitate the interface between the grout and the sliding plates beneath the footings. The solution was designed to restore the integrity of the insulation system and ensure the tanks remain stable under cyclic loads. Key steps included:

Surface Preparation

Material Removal: Pneumatic chippers were used to remove approximately 50 mm of the degraded grout from underneath the sliding plates.

Leveling: The team ensured that the exposed concrete was healthy and level without altering the saddleโ€™s position.

Installation of Alphapadsยฎ and Regrouting

Alphapadsยฎ Placement: Alphapadsยฎ (sized D2) were set in place and adjusted to the correct height, enabling the hydraulic levelling system to work effectively.

Epoxy Grouting: ALPHATECยฎ 800 epoxy grout was carefully applied to the interface between the sliding plates and the newly prepared surface beneath the footings. This process ensured that the full weight of the tank was transferred securely onto the grout.

Final Checks and Quality Assurance

A thorough inspection verified that all grouted areas were properly aligned and free from sharp edges.

The repair work was conducted on all six footings of the two parallel tanks, reinforcing the foundation for long-term stability.

03

Outcome and Impact

Following the repair, the HTF tank footings demonstrated restored stability and improved insulation performance. The comprehensive grout restoration reduced the adverse effects of cyclic loading and minimised further degradation, ensuring that the thermal storage system continues to operate reliably. This successful intervention underscores the importance of meticulous surface preparation and precise regrouting in the renewable energy sector.

By addressing these critical issues with targeted repairs and advanced materials, Alphatec Engineering has ensured that the Andasol solar power stationโ€™s HTF tanks remain robust against temperature-induced stresses, contributing to the plantโ€™s overall efficiency and sustainability in renewable energy production.